The SWMA Monitoring team, led by the Municipal Coordinating Director on, behalf of the Municipal Chief Executive and the Consultant inspected the Ghana Secondary Cities Project UDG II in the Sefwi Dwenase Market.
The inspection followed up with a site meeting with the contractors, and the Consultant of the project where the consultant of the project, Mr. Ansong briefed the team on the progress of work done so far. He added that, site clearance and excavation works have been done whilst reinforcement and blockwork in the foundation have also been completed. Again, he said, Compaction is 50% complete.
The Municipal Coordinating Director, Mr. Joseph K. Baah – Darkoh expressed satisfactory of the progress of work during the inspection and stated that quality standard of work has remain a major priority of the team. He then charged the contractors to work according to the specification of the project and adhere to the timelines.